What permits and procedures are required to add rooftop solar panels to a Turkish home, and can excess power be net-metered?

Short answer and scope

You apply to your local electricity distribution company under Turkey’s “unlicensed generation” regime; after connection with a bidirectional meter, any surplus shows up as a monetary settlement on your electricity bill rather than classic retail net metering.[1][2][4][8] The rules come from the Electricity Market Law and secondary regulations, and you may also need municipal clearance under zoning rules and, in apartment buildings, a condominium owners’ decision for roof use.[1][2][5][6] The process is administrative—no generation license—but it is formal and document-heavy.[2][3]

Legal basis and where applications are made

Article 14 of the Electricity Market Law No. 6446 exempts small, behind-the-meter projects from licensing if they meet secondary legislation conditions and connect through the distribution network.[1] The Regulation on Unlicensed Electricity Generation defines self-consumption at the same connection point, sets capacity and siting rules, and puts the application and connection workflow in the hands of the regional distribution company.[2] After a positive connection opinion, you sign a connection agreement and a system usage agreement under the Regulation on Connection and System Use.[3] Metering must comply with the Regulation on Metering Systems, using certified devices that record energy taken from and delivered to the grid.[4]

Building and condominium rules affecting the roof

The Planned Areas Zoning Regulation allows technical equipment such as solar panels on roofs and façades within height and architectural limits overseen by municipalities, which run any permit or notification steps.[5] In condominiums (kat mülkiyeti), the roof is a common area; adding installations to common parts requires an owners’ assembly resolution, and improvements beyond ordinary maintenance generally need a four-fifths majority under Condominium Law No. 634.[6] Detached houses on their own parcel avoid condominium voting but may still face municipal project submission or minor-works permit requirements depending on panel layout and anchoring.[5]

Capacity limits and siting under unlicensed generation

Household rooftop systems are sized to the consumption at the same connection point. Distribution companies check your contracted connection power and local grid limits when issuing the preliminary connection opinion.[2][3] Self-consumption plants must be physically tied to the consumption site or otherwise comply with the association rules in the unlicensed regulation, and you cannot feed power into the network without executed connection and system use agreements.[2][3] In multi-unit buildings, any allocation of produced energy must align with condominium rules and the single-connection-point structure in the unlicensed regime.[2][6]

Application file, technical approval, and commissioning

File your application with the regional distribution company for your address, using the forms and annexes under the unlicensed regulation. Provide identification, proof of ownership or right to use the roof, a single-line diagram and panel layout by a licensed electrical engineer, and the condominium owners’ resolution if the roof is common property.[2][6] If you receive a positive preliminary connection opinion, complete the technical project, sign the connection and system use agreements, and install the system.[2][3] Before energization, the distribution company replaces the meter with a bidirectional, compliant device and performs or witnesses acceptance tests for protection and anti-islanding per connection standards.[3][4] The company then issues the commissioning record, and the system operates under unlicensed rules linked to your retail account.[2][3][4]

Metering and how surplus energy is settled

Household rooftop production under the unlicensed regime is settled on your retail electricity bill, not through separate wholesale registration. The metering regulation requires hour-by-hour records of imports and exports with a certified meter, allowing the distribution company and your supplier to calculate net consumption and any surplus.[4] The unlicensed regulation and market procedures use these readings to offset consumption at the same connection point and assign a monetary value to remaining surplus based on EMRA-published retail tariff components for your subscriber group; the results appear on your supplier invoice under the applicable unlicensed procedures.[2][7][8] This is not classic net metering with rolling kWh credits; it is bill-based settlement at values set by EMRA for the relevant period.[2][7][8]

Practical next step and timing

Start by asking your regional distribution company for the current unlicensed rooftop solar application pack and a connection capacity check for your address. At the same time, request from your building manager the condominium management plan and any roof-use decisions, and meet a licensed electrical engineer early to align the layout with municipal zoning and metering/protection requirements before collecting signatures and paying fees.[2][3][4][5] Because tariffs and settlement procedures change by EMRA decision, review the latest retail tariff tables and ask your supplier how unlicensed residential surplus appears on invoices for your subscriber class. This is general information; for design, permits, and economics, work with licensed professionals for your building and utility zone.[2][4][8]

Related Questions:
– How do I get a connection agreement with my Turkish electricity distribution company?
– Do I need a building permit for exterior works on a Turkish home?
– What decisions can a condominium owners’ assembly make about common areas like roofs?
– How are residential electricity tariffs structured in Turkey?

References:
[1] Official Gazette (Resmi Gazete). “Electricity Market Law No. 6446.” https://www.mevzuat.gov.tr/MevzuatMetin/1.5.6446.pdf
[2] Official Gazette (Resmi Gazete). “Regulation on Unlicensed Electricity Generation in the Electricity Market (Elektrik Piyasasında Lisanssız Elektrik Üretim Yönetmeliği), as amended.” https://www.resmigazete.gov.tr/eskiler/2013/10/20131002-7.htm
[3] Official Gazette (Resmi Gazete). “Regulation on Connection and System Use in the Electricity Market (Elektrik Piyasasında Bağlantı ve Sistem Kullanımı Hakkında Yönetmelik).” https://www.resmigazete.gov.tr/eskiler/2014/01/20140128-5.htm
[4] Official Gazette (Resmi Gazete). “Regulation on Metering Systems in the Electricity Market (Elektrik Piyasasında Ölçüm Sistemleri Yönetmeliği).” https://www.resmigazete.gov.tr/eskiler/2020/12/20201228-5.htm
[5] Official Gazette (Resmi Gazete). “Planned Areas Zoning Regulation (Planlı Alanlar İmar Yönetmeliği).” https://www.resmigazete.gov.tr/eskiler/2017/07/20170703-7.htm
[6] Official Gazette (Resmi Gazete). “Condominium Law No. 634 (Kat Mülkiyeti Kanunu).” https://www.mevzuat.gov.tr/MevzuatMetin/1.3.634.pdf
[7] EPİAŞ (Energy Markets Operator). “Unlicensed Generation Portal (Lisanssız Üretim Portalı) – Information on settlement.” https://lisanssiz.epias.com.tr/
[8] Energy Market Regulatory Authority (EMRA/EPDK). “Electricity – Tariffs and Publications.” https://www.epdk.gov.tr/Detay/Icerik/3-0-0-0/elektrik

Disclaimer: This article is for informational purposes only and does not constitute legal, financial, or investment advice. Property law and tax rules in Turkey change frequently. Consult a licensed Turkish lawyer, accountant, or real estate professional before making any purchasing decision.

Related Articles